US PPI — Elevator and Moving Stairway Manufacturing

Producer Price Index for elevator and moving stairway manufacturing.

261.359+0.0% m/m+2.5% y/y+34.5% 5y

Sep 2026 value · Next print expected around Nov 2026 · Source: BLS

Price history

Sep 2026 · latest261.359+34.5%since Sep 2021
18020022024026028020222023202420252026261.4
Move along the line to read any month

Copy the values

Paste straight into Excel, Google Sheets or an email. Spreadsheet format lands as two columns.

Range
Format

Preview13 rows, newest first. Click a value to copy it.
MonthValueChange m/m
Sep 2026+0.0%
Aug 2026+0.2%
Jul 2026+0.6%
Jun 2026+0.1%
May 2026−0.4%
Apr 2026+0.1%
Mar 2026+0.1%
Feb 2026+0.0%
Jan 2026+1.6%
Dec 2025+0.2%
Nov 2025+0.1%
Oct 2025−0.1%
Sep 2025+0.0%

Same numbers as the chart, straight from BLS. Dates are the first of each period, the way BLS reports them.

How it's built

Elevators rose 2.5% over the last 12 months, but all of its main inputs rose faster: copper wire and cable +30.8%, steel mill products +27.6%. That cost pressure may still pass through to prices.

Key figures

Since Jan 2017
+55.7%
167.9 to 261.4
12-month volatility
±0.5%
std. dev. of monthly change
Largest monthly rise
+7.5%
Dec 2021
10% cap would bind
0 of 36
months, annual base reset
  • From Jan 2017 to Sep 2026 the index went from 167.9 to 261.4, a change of +55.7%.
  • Highest reading in that period: 261.4 in Sep 2026. Lowest: 167.9 in Jan 2017.
  • Largest one-month rise: +7.5% in Dec 2021. Largest one-month fall: -0.6% in Mar 2022.
  • The year-over-year change stayed within 10% either way in each of the last 36 months, so a 10% annual cap or floor would not have been reached.

Use it in a contract

Draft clause citing this series

A starting point citing this series by name and code. Replace the bracketed terms with your contract's actual scope before use.

The [affected portion] of the Contract Price shall be adjusted using US PPI — Elevator and Moving Stairway Manufacturing (BLS series PCU333921333921), published by BLS.

Base Period: the index value published for September 2026 (or the month of contract signing, if different) is the Base Value.

Adjustment: at each Adjustment Date, the Current Value is the most recently published three-month average of the index (the Averaging Window). The Escalation Factor equals Current Value divided by Base Value.

Cap: the Escalation Factor applied under this clause shall not exceed 1.10 or fall below 0.90 (a 10% cap and floor) in any single Adjustment Date, regardless of the index's actual movement.

[Replace bracketed terms with your contract's actual affected-portion definition and adjustment-date schedule before use. This is a drafting starting point, not legal advice.]
Why contracts cite this index

A narrow but real line in a high-rise or commercial construction contract, elevator equipment cost tracks separately from general building materials.

How this index is used (1 guide)

What is price escalation in a construction contract?

Price escalation in a construction contract is a clause that adjusts the contract price for movements in the published price of a named material, fuel, or labor cost after the bid. It shifts material-price risk from the contractor to the owner, within a defined base period, formula, and cap.

Let Escalake run this clause for you

Escalake tracks US PPI — Elevator and Moving Stairway Manufacturing, applies your formula, and gives both sides a number they can confirm, no spreadsheet required.