US PPI — Power, Distribution, and Specialty Transformer Manufacturing

Producer Price Index for electrical transformers, updated monthly.

475.065+0.0% m/m+7.8% y/y+50.4% 5y

Sep 2026 value · Next print expected around Nov 2026 · Source: BLS

Price history

Sep 2026 · latest475.065+50.4%since Sep 2021
30035040045050020222023202420252026475.1
Move along the line to read any month

Copy the values

Paste straight into Excel, Google Sheets or an email. Spreadsheet format lands as two columns.

Range
Format

Preview13 rows, newest first. Click a value to copy it.
MonthValueChange m/m
Sep 2026+0.0%
Aug 2026+0.0%
Jul 2026+4.0%
Jun 2026+0.0%
May 2026+0.5%
Apr 2026−0.4%
Mar 2026+0.0%
Feb 2026+0.0%
Jan 2026+0.0%
Dec 2025+0.0%
Nov 2025−0.6%
Oct 2025+4.0%
Sep 2025+0.0%

Same numbers as the chart, straight from BLS. Dates are the first of each period, the way BLS reports them.

How it's built

Transformers rose 7.8% over the last 12 months, but all of its main inputs rose faster: cold rolled steel sheet and strip +36.9%, copper wire and cable +30.8%. That cost pressure may still pass through to prices.

Key figures

Since Jan 2017
+105.2%
231.5 to 475.1
12-month volatility
±1.5%
std. dev. of monthly change
Largest monthly rise
+6.0%
Jun 2021
10% cap would bind
0 of 36
months, annual base reset
  • From Jan 2017 to Sep 2026 the index went from 231.5 to 475.1, a change of +105.2%.
  • Highest reading in that period: 475.1 in Aug 2026. Lowest: 231.5 in Jan 2017.
  • Largest one-month rise: +6.0% in Jun 2021. Largest one-month fall: -2.5% in Oct 2022.
  • The year-over-year change stayed within 10% either way in each of the last 36 months, so a 10% annual cap or floor would not have been reached.

Use it in a contract

Draft clause citing this series

A starting point citing this series by name and code. Replace the bracketed terms with your contract's actual scope before use.

The [affected portion] of the Contract Price shall be adjusted using US PPI — Power, Distribution, and Specialty Transformer Manufacturing (BLS series PCU335311335311), published by BLS.

Base Period: the index value published for September 2026 (or the month of contract signing, if different) is the Base Value.

Adjustment: at each Adjustment Date, the Current Value is the most recently published three-month average of the index (the Averaging Window). The Escalation Factor equals Current Value divided by Base Value.

Cap: the Escalation Factor applied under this clause shall not exceed 1.10 or fall below 0.90 (a 10% cap and floor) in any single Adjustment Date, regardless of the index's actual movement.

[Replace bracketed terms with your contract's actual affected-portion definition and adjustment-date schedule before use. This is a drafting starting point, not legal advice.]
Why contracts cite this index

One of the strongest indexed components in data-center, transmission, and substation contracts, a real manufactured product with a live monthly survey.

How this index is used (2 guides)

How do you structure a price escalation clause for telecom infrastructure contracts?

Split the contract by what is being built: towers, fiber, data centers, or core network equipment. Towers, fiber and data centers have no single official price index for the finished project, so use a weighted composite of real cost inputs. Data centers have the best coverage: transformers (PCU335311335311) and switchgear (PCU335313335313) both have real, live BLS indices.

Let Escalake run this clause for you

Escalake tracks US PPI — Power, Distribution, and Specialty Transformer Manufacturing, applies your formula, and gives both sides a number they can confirm, no spreadsheet required.